Hazardous Material Management System
System: Hosted in DLA Azure Government enclave (IL5, ATO/RMF compliant). PIV card authentication. No day-one purchasing integration — manual flat-file is interim. Legacy Oracle/ColdFusion CMS to be retired.
Decisions Required
Confirm Overall HMMS Implementation Lead
Luz or Steve Herron — not yet confirmed. Fragmented authority creates decision paralysis across all workstreams. Must be named before any module configuration begins.
Immediate
Authorize NDA for Data Dictionary Release
Larry Sivic requested architecture, integration, and data dictionary briefing. NDA must be executed before Sphera can release table structures. Blocks the architecture meeting.
Before Arch. Mtg
Activate HMMS Authorization (AUL) Workflow at Go-Live?
Determines whether Environmental, Safety, IH, and Logistics review and approval routing is configured into HMMS from day one, or deferred to a later phase. Directly affects configuration scope.
Before Config Start
Define Issue Model
Materials issued to: employees, lockers, or locations? Determines how users and employees are configured in HMMS and drives training design for all end users.
Before User Setup
Consumer-Use Product Inclusion Rule
Define the criteria for including or excluding minor consumer-use products. Directly sets inventory scope and onsite workload for the fence-to-fence inventory.
Before Inventory
Critical Path
| Item | Owner | Due | Status |
|---|---|---|---|
| Extract & submit SDS list from Oracle CMSChemical name, manufacturer, SDS #, revision date | Lisa Ramsey / Frank / Benjamin | ASAP | Open |
| Submit updated HazMat inventory listSize, unit, quantity, location, barcode bridge | Site Materials SMEs | ASAP | Open |
| Submit all Static Data Migration spreadsheetsBuildings, zones, issue points, employees, waste profiles, users | Site Leads | 60 days pre-onsite | Open |
| Resolve scanner / hardware standardHoneywell EOL; Class I Div 2 areas require intrinsically safe devices | Harry Stein / OCIO | June 17 Meeting | Decision Gate |
| Build stage sandbox with sample dataOne issue point, one shop, sample SDS for champion demos | Kylan / Sphera | Before Site Visit | Open |
| Submit all AMPS/NAMS account access requestsRequires supervisor + Protective Services approval chain | Harry / Site Users | ASAP | Open |
| Complete HazWOPER training for relevant personnelMust complete before onsite HMMS activities begin | Lisa Ramsey / Anna Morgan | Sept 3, 2026 | Needs Confirmation |
Key Risks
| Risk | Likelihood | Impact | Mitigation |
|---|---|---|---|
| Pre-implementation data submitted lateSDS list, inventory, static data — up to 60-day delay if missed | High | Critical | ✓ Hard deadlines + NASA PM audit trigger |
| Governance not confirmedHMMS lead, module leads, AUL review group all unresolved | High | High | ✓ Escalation path to Larry Sivic identified |
| Scanner / hardware standard unresolvedHoneywell EOL; Class I Div 2 needs intrinsically safe devices | Medium | High | ⚠ June 17 meeting is gate — no fallback documented yet |
| Stage environment has skeleton data onlyChampions can't visualize future state; risks buy-in and training readiness | Medium | High | ✓ Action assigned to Kylan/Sphera before site visit |
| Key waste SME unavailable week of Sept 7John Bonar (manifest/profile) — critical waste module dependency | Known | High | ✓ Avoid scheduling waste config that week; backups named |
| End-user resistance to changePersonnel accustomed to Oracle CMS; change management not yet activated | Medium | High | ✓ Change champions + Larry Sivic visible sponsorship |
| IT / cybersecurity access delaysNAMS account creation requires supervisor + Protective Services approval | Medium | Medium | ✓ Early AMPS submission; Burke & Gullett engaged |
| Site unprepared at Tiger Team arrivalBadging, IT, PPE, and data not complete on arrival day | Medium | High | ✓ 90-day pre-arrival checklist + NASA PM audit enforcement |
Key Milestones
Program Deliverables
| # | Deliverable | Status |
|---|---|---|
| 1 | Site Profile & Governance StructureAll named leads confirmed: HazMat, Waste, Environmental, IH, Safety, Logistics, OCIO | Partial |
| 2 | Complete Static Data PackageSDS, inventory, employees, buildings, zones, issue points, waste profiles, users | Open |
| 3 | Stage / Sandbox EnvironmentSample data loaded for champion review and training prep | Open |
| 4 | Workflow Crosswalk & Local HMMS SOPAll 9 lifecycle stages: procurement to disposal to reporting | Partial |
| 5 | HMMS Configuration BuildLocation hierarchy, user model, AUL workflow, waste module, barcode/scanner setup | Open — awaiting decisions |
| 6 | Fence-to-Fence Inventory (90%+ barcoded)All designated areas: storage, shops, labs, waste sites | Not Started |
| 7 | Role-Based Training95%+ proficiency; training records, job aids, SOPs delivered | Not Started |
| 8 | Compliance Reporting ActivatedJasperSoft dashboards, scheduled reports, EPCRA/RCRA/TRI validated | Not Started |
| 9 | Formal Go-Live Sign-Off & Tiger Team DemobilizationFinal walkthrough, stress test, NASA GRC leadership signature | Not Started |
| 10 | Legacy Oracle CMS Retirement PlanSystems to retire documented; data retention requirements confirmed | Open |